# Objective
- Systems that use the task pool, either explicitly or implicitly using
parallel queries, will often end up executing tasks from different
systems.
- This can cause random tasks to block the main or render schedule at
random, adding frame variance and increasing frame times when CPU bound.
- This profile is a common occurrence on `main`.
`propagate_parent_transforms` takes more than twice as long as it
should, blocking the main schedule for that time, because it uses `task
pool.scope`, which has decided to execute tasks from the render schedule
on the main schedule.

## Solution
- In task pool scope execution, prefer to check if the current task is
complete instead of ticking the executor to find new work.
## Testing
- Ran the scene viewer with tracy to look for images like the one in the
objective section.
- Things look much, much better, and I could not find any occurrences: